Watervliet substation interconnection queue
2 active projects totaling 5.5 MW in the PJM queue.
2 PJM queue filings name Watervliet as the point of interconnection, all in Berrien County, MI.
Target commercial operation dates as filed run from Nov 2012 to Dec 2016 (2 filings).
2active projects
5.5active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| X1-042 | Orchard Hills | n/r | 3.2 | Gas | In Service | Nov 2012 |
| Z2-113 | Watervliet Solar Facility | 12.5 | 2.3 | Solar | In Service | Dec 2016 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Berrien County, MI
- Olive - Cook: 3 active, 478.8 MW of 3 filed
- Blossom Trail: 1 active, 150 MW of 2 filed
- DC Cook Unit 2: 2 active, 121 MW of 2 filed
- Cook: 1 active, 84 MW of 2 filed
Site Scanner