Substation Scout

Berrien, MI interconnection queue

15 active projects totalling 1,301 MW in the PJM queue, plus 5 with terminal status (shown greyed).

15active projects
1,301active MW
20total filed
Queue IDProjectkVMWResourceStatus
N46 Cook 345kV 345 1,120 Gas Withdrawn
C01-2194 Olive - Cook 345 kV 345 300 Battery Active
C01-1350 Sodus 138 kV 138 200 Battery Active
C01-1596 Blossom Trail 138kV 138 kV 138 150 Battery Active
C01-1787 Derby 138 kV 138 150 Battery Active
AH2-373 Blossom Trail 138 kV 138 132 Hybrid Withdrawn
AH2-418 Riverside - Pokagon 138 kV 138 100 Hybrid Withdrawn
C01-1742 Riverside - Blossom Trail 138 kV 138 100 Battery Withdrawn
C01-2048 Pokagon 138kV (sub) - Riverside Station 138kV 138 kV 138 95 Hybrid Active
C01-1595 Sodus - Kenzie Creek 138 kV 138 90 Solar Withdrawn
C01-2195 Olive - Cook 345 kV 345 89.4 Wind Active
C01-2196 Olive - Cook 345 kV 345 89.4 Wind Active
O42 Cook #1 345 84 Nuclear In Service
Z1-051 D.C. Cook Generating Plant Unit No. 2 n/r 83 Nuclear In Service
AC2-140 DC Cook Generating Plant Unit No. 2 n/r 38 Nuclear In Service
C01-1257 DC Cook 345 kV 345 9.5 Nuclear Active
T111 Southeast Berrien LF 69 6.4 Gas In Service
X1-042 Orchard Hills n/r 3.2 Gas In Service
Z2-113 Watervliet Solar Facility 12.5 2.3 Solar In Service
AE1-039 Orchard Hills Sanitary Landfill 12.5 0.8 Gas In Service

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.