Sandwich-Plano substation interconnection queue

2 active projects totaling 167.5 MW in the PJM queue, plus 3 with terminal status (shown grayed).

5 PJM queue filings name Sandwich-Plano as the point of interconnection, all in Kendall County, IL.

Target commercial operation dates as filed run from Dec 2022 to May 2030 (5 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: ComEd (3 filings).

2active projects
167.5active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE2-340 Sandwich-Plano n/r 208.8 Battery Withdrawn Dec 2022
AE2-341 Plano Skies Energy Center 138 100.6 Solar EP May 2030
AF1-030 Plano Skies Energy Center 138 66.9 Solar EP May 2030
AG2-316 Sandwich-Plano 138 KV 138 49.4 Battery Withdrawn Dec 2023
AF2-329 Sandwich-Plano 138 kV 138 42.2 Battery Withdrawn Dec 2023

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Kendall County, IL

All 17 PJM queue filings in Kendall County, IL.