Plano Skies Energy Center (AF1-030) is listed in the PJM interconnection queue as a 66.9 MW solar project in Kendall County, IL. The filing names Sandwich-Plano as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of May 30, 2030.

Queue IDAF1-030
Project namePlano Skies Energy Center
Status (as published)EP
SubstationSandwich-Plano
Point of interconnectionSandwich-Plano 138 kV
CountyKendall
StateIL
Voltage138 kV
Capacity66.9 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2030-05-30
Source datasetcycle

Same substation and county

Sandwich-Plano substation: 5 requests in the PJM queue, 2 active totaling 167.5 MW.

Queue IDProjectMWResourceStatus
AE2-341Plano Skies Energy Center100.6SolarEP
AE2-340Sandwich-Plano208.8BatteryWithdrawn
AG2-316Sandwich-Plano 138 KV49.4BatteryWithdrawn
AF2-329Sandwich-Plano 138 kV42.2BatteryWithdrawn

Kendall, IL: 17 requests in the PJM queue, 3 active totaling 467.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperPlano Skies Energy Center, LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
MW energy100.0
MW capacity66.9
MFO250.0
Submitted date5/17/2019
Last updated8/18/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.