Substation Scout

Pendleton substation interconnection queue

1 active project totalling 11.2 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
11.2active MW
2total filed
Queue IDProjectkVMWResourceStatus
W3-043 Pendleton 230 kV 230 65 Offshore Wind Withdrawn
AC1-027 Oceana Solar Facility 34.5 11.2 Solar In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.