PJM queue ID N12

North Haverhill (N12) is listed in the PJM interconnection queue as a 75 MW coal project in Scioto County, OH. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2009.

Queue IDN12
Project nameNorth Haverhill
Status (as published)In Service
SubstationNorth Haverhill
Point of interconnectionNorth Haverhill 69 kV
CountyScioto
StateOH
Voltage69 kV
Capacity75 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Target commercial operation2009-06-01
Source datasetserial

Same substation and county

North Haverhill substation: 2 requests in the PJM queue, 1 active totaling 75 MW.

Queue IDProjectMWResourceStatus
T152North Haverhill 69kV140CoalWithdrawn

Scioto, OH: 7 requests in the PJM queue, 1 active totaling 75 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy75
MW capacity75
MFO75

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first