La Rue substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name La Rue as the point of interconnection, all in Marion County, OH.
Target commercial operation dates as filed run from Dec 2024 to Mar 2025 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-218 | La Rue 69 kV | 69 | 32 | Solar | Withdrawn | Dec 2024 |
| AH2-344 | La Rue 138 kV | 138 | 30.2 | Hybrid | Withdrawn | Mar 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Marion County, OH
- Galion-Roberts South: 1 active, 62.1 MW of 2 filed
- Galion-Roberts South II: none active of 2 filed
- Roberts: none active of 2 filed
- South Morral-Uncapher Switch: none active of 2 filed