Highland-Sammis & Highland-Mansfield substation interconnection queue
2 active projects totalling 864 MW in the PJM queue.
2active projects
864active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| Z2-028 | Lordstown Energy Center | 345 | 800 | Gas | In Service |
| AB1-017 | Lordstown Energy Center | 345 | 64 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.