Highland-Hanna substation interconnection queue

1 active project totaling 850 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Highland-Hanna as the point of interconnection, all in Trumbull County, OH.

Target commercial operation dates as filed run from Oct 2020 to Jan 2026 (2 filings).

1active projects
850active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AB1-105 Trumbull Energy Center 345 850 Gas In Service Jan 2026
AD2-057 Highland-Hanna 345kV 345 850 Gas Withdrawn Oct 2020

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.