Grays Ferry substation interconnection queue
1 active project totaling 13 MW in the PJM queue, plus 2 with terminal status (shown grayed).
3 PJM queue filings name Grays Ferry as the point of interconnection, all in Philadelphia County, PA.
Target commercial operation dates as filed run from May 2011 to Jun 2022 (3 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| W1-108 | Grays Ferry Cogeneration Partnership | 230 | 13 | Gas | In Service | Jun 2011 |
| AH1-648 | Grays Ferry 230kV | 230 | 5 | Gas | Withdrawn | Jun 2022 |
| W4-085 | Grays Ferry | n/r | 0 | Battery | Withdrawn | May 2011 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Grays Ferry (PECO, 1 mention).
Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.
Other PJM queue substations in Philadelphia County, PA
- Chichester: 2 active, 750 MW of 2 filed
- Richmond: 1 active, 2 MW of 7 filed
- Passyunk: none active of 3 filed
- Penrose #2: none active of 2 filed