Grays Ferry Cogeneration Partnership
PJM queue ID W1-108
Grays Ferry Cogeneration Partnership (W1-108) is listed in the PJM interconnection queue as a 13 MW gas project in Philadelphia County, PA. The filing names Grays Ferry as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2011.
| Queue ID | W1-108 |
|---|---|
| Project name | Grays Ferry Cogeneration Partnership |
| Status (as published) | In Service |
| Substation | Grays Ferry |
| Point of interconnection | Grays Ferry 230kV |
| County | Philadelphia |
| State | PA |
| Voltage | 230 kV |
| Capacity | 13 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2011-06-01 |
| Source dataset | serial |
Same substation and county
Grays Ferry substation: 3 requests in the PJM queue, 1 active totaling 13 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AH1-648 | Grays Ferry 230kV | 5 | Gas | Withdrawn |
| W4-085 | Grays Ferry | 0 | Battery | Withdrawn |
Philadelphia, PA: 24 requests in the PJM queue, 4 active totaling 765 MW.
A substation with the same name is named in PJM transmission planning materials: Grays Ferry (PECO, 1 mention).
Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 13 |
| MW capacity | 13 |
| MFO | 163 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.