Philadelphia, PA interconnection queue

4 active projects totalling 765 MW in the PJM queue, plus 20 with terminal status (shown greyed).

4active projects
765active MW
24total filed
Queue IDProjectkVMWResourceStatus
A21 Phillips Island 230 725 Gas In Service
U1-012 Richmond n/r 630 Gas Withdrawn
G45 Richmond n/r 575 Gas Withdrawn
H08 Richmond 230kV 230 560 Gas Withdrawn
D28 Passyunk 230kV 230 550 Gas Withdrawn
A27 Passyunk 230 kV 230 515 Gas Withdrawn
AA2-077 Penrose #1 230kV 230 220 Gas Withdrawn
AA2-050 Penrose #1 230klV n/r 210 Gas Withdrawn
O64 Grays Ferry - Island Road n/r 201 Gas Withdrawn
AA2-051 Penrose #2 230kV 230 130 Gas Withdrawn
AA2-078 Penrose #2 230kV 230 130 Gas Withdrawn
G07 Richmond n/r 100 Gas Withdrawn
M09 Island Road n/r 50 Not reported Withdrawn
H06 Phillips Island 230 25 Gas In Service
T113 Richmond 230kV 230 16 Other Withdrawn
W1-108 Grays Ferry Cogeneration Partnership 230 13 Gas In Service
W4-051 Packer 13kV 13 10.2 Gas Withdrawn
AH1-648 Grays Ferry 230kV 230 5 Gas Withdrawn
W2-014 Richmond n/r 2 Other In Service
Z1-115 Crescentville 13kV 13 1 Gas Withdrawn
X4-045 Southwark 13kV 13 0.1 Battery Withdrawn
AB1-074 Richmond 230kV 230 0 Battery Withdrawn
U2-029 Passyunk n/r 0 Solar Withdrawn
W4-085 Grays Ferry n/r 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.