Garner DP-Lancaster substation interconnection queue
3 active projects totaling 68.7 MW in the PJM queue, plus 4 with terminal status (shown grayed).
7 PJM queue filings name Garner DP-Lancaster as the point of interconnection, all in Lancaster County, VA.
Target commercial operation dates as filed run from Jun 2024 to Dec 2027 (7 filings). 3 active filings target a date after November 27, 2026.
Transmission owner as filed: Dominion (3 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI2-237 | Garner DP-Lancaster 115 kV | 115 | 69.3 | Solar | Withdrawn | Jun 2024 |
| AG1-147 | Merry Point Solar | 115 | 42 | Solar | Withdrawn | Dec 2024 |
| AG2-215 | Garner DP-Lancaster 115 kV | 115 | 36.9 | Solar | Withdrawn | Dec 2027 |
| AD2-074 | Waller Solar I | 115 | 32.7 | Solar | Under Construction | Dec 2027 |
| AG1-038 | Waller Solar I | 115 | 18.9 | Solar | Under Construction | Dec 2027 |
| AG1-146 | Merry Point Solar | 115 | 18 | Solar | Withdrawn | Dec 2024 |
| AF1-042 | Waller Solar I | 115 | 17.1 | Solar | Under Construction | Dec 2027 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Tracked changes at this substation
2 changes to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-11-09 | AG1-038 | Status change | n/a | Engineering and Procurement → Under Construction |
| 2026-11-09 | AF1-042 | Status change | n/a | Engineering and Procurement → Under Construction |
Other PJM queue substations in Lancaster County, VA
- Garner-Lancaster: 1 active, 36 MW of 3 filed
- Garner Delivery Point - Lancaster: none active of 2 filed