Galion substation interconnection queue
3 active projects totaling 669.5 MW in the PJM queue, plus 1 with terminal status (shown grayed).
4 PJM queue filings name Galion as the point of interconnection, all in Morrow County, OH.
Target commercial operation dates as filed run from Dec 2012 to Aug 2031 (4 filings). 3 active filings target a date after November 27, 2026.
Transmission owner as filed: ATSI (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-1805 | Galion 345 kV | 345 | 332.5 | Battery | Active | Oct 2029 |
| C01-1377 | Galion 345 kV | 345 | 300 | Battery | Active | Aug 2031 |
| AF2-150 | Blossom Solar | 138 | 37 | Solar | Under Construction | Jul 2027 |
| V2-042A_AT2 | Galion 138kV | 138 | 26 | Wind | Withdrawn | Dec 2012 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Galion (ATSI, 8 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Other PJM queue substations in Morrow County, OH
- Cardington: 1 active, 200 MW of 2 filed