Galion 345 kV

PJM queue ID C01-1805

Queue IDC01-1805
Project nameGalion 345 kV
Status (as published)Active
SubstationGalion
Point of interconnectionGalion 345 kV
CountyMorrow
StateOH
Voltage345 kV
Capacity332.5 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-10-01
Source datasetcycle

Additional filed fields

DeveloperOrchid Storage, LLC
Transmission OwnerATSI
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy350.0
Mw Capacity332.5
Mfo350.0
Submitted Date4/23/2026
Last Updated6/22/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.