Essex substation interconnection queue

6 active projects totalling 714 MW in the PJM queue, plus 14 with terminal status (shown greyed).

6active projects
714active MW
20total filed
Queue IDProjectkVMWResourceStatus
X2-050 Essex 230kV 230 660 Gas Withdrawn
S04 Essex 230kV 230 633 Gas Withdrawn
T107 Newark Energy Center 230 625 Gas In Service
T44 Essex 230kV 230 205 Gas Withdrawn
Y2-083 Essex 138kV 138 198 Gas Withdrawn
T43 Essex 230kV 230 178 Gas Withdrawn
U1-097 Essex 230kV 230 100 Gas Withdrawn
S60 Newark Boxboard 26 63 Gas Withdrawn
Y2-019 Newark Energy Center 230 45 Gas In Service
AG1-268 Essex 230 kV 230 40.8 Battery Withdrawn
AG2-224 Essex 230 kV 230 36 Battery Withdrawn
X3-004 Newark Energy Center 230 35 Gas In Service
L12 Essex n/r 6.2 Gas Withdrawn
G20 Essex 9 n/r 6 Gas In Service
Y3-047 Essex n/r 6 Gas Withdrawn
AA2-052 Essex 26kV 26 3 Gas In Service
V2-012 Essex SP 26.4 2.8 Gas Withdrawn
AH1-006 Essex 26 kV 26 2.2 Solar Withdrawn
W4-034 Essex 26.4kV 26.4 0 Gas Withdrawn
X3-052 Essex County Correctional Facility 26.4 0 Gas In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.