Edgecombe substation interconnection queue
1 active project
totalling 100 MW in the PJM queue, plus 1 with terminal status (shown greyed).
1 active projects
100 active MW
2 total filed
Queue ID Project kV MW Resource Status
AF2-303
Swift Creek Solar
230
100
Hybrid
Engineering and Procurement
AF2-324
Edgecombe 230 kV
230
45
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with PJM before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.