Substation Scout

Swift Creek Solar

PJM queue ID AF2-303

Swift Creek Solar (AF2-303) is listed in the PJM interconnection queue as a 100 MW hybrid project in Edgecombe County, NC. The filing names Edgecombe as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of September 1, 2029.

Queue IDAF2-303
Project nameSwift Creek Solar
Status (as published)Engineering and Procurement
SubstationEdgecombe
Point of interconnectionEdgecombe 230 kV
CountyEdgecombe
StateNC
Voltage230 kV
Capacity100 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalized for filtering)
Target commercial operation2029-09-01
Source datasetserial

Same substation and county

Edgecombe substation: 2 requests in the PJM queue, 1 active totaling 100 MW.

Queue IDProjectMWResourceStatus
AF2-324Edgecombe 230 kV45SolarWithdrawn

Edgecombe, NC: 23 requests in the PJM queue, 8 active totaling 341.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy100
MW capacity100
MFO100

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.