Substation Scout

Benson-Dunbar substation interconnection queue

1 active project totalling 66 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
66active MW
2total filed
Queue IDProjectkVMWResourceStatus
AB2-059 Moccasin Creek Solar 115 66 Solar In Service
AI2-299 Benson-Dunbar 115 kV 115 30.8 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.