East Fayette substation interconnection queue

2 active projects totalling 163.3 MW in the PJM queue.

2active projects
163.3active MW
2total filed
Queue IDProjectkVMWResourceStatus
AF1-206 CG Fulton County 138 119.4 Solar Engineering and Procurement
AE2-282 Arche Energy Project 138 43.9 Solar In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.