East Fayette substation interconnection queue
2 active projects totaling 163.3 MW in the PJM queue.
2 PJM queue filings name East Fayette as the point of interconnection, all in Fulton County, OH.
Target commercial operation dates as filed run from Dec 2023 to May 2028 (2 filings). 1 active filing targets a date after November 27, 2026.
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF1-206 | CG Fulton County | 138 | 119.4 | Solar | Engineering and Procurement | May 2028 |
| AE2-282 | Arche Energy Project | 138 | 43.9 | Solar | In Service | Dec 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Same name on other Substation Scout pages
Other sources that print a substation named “East Fayette” in OH. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- East Fayette: Expansion Tracker, PJM planning: AMPT state not printed
- East Fayette: Expansion Tracker, PJM planning: ATSI state not printed
Other PJM queue substations in Fulton County, OH
- Allen Junction: none active of 3 filed
- Fulton: none active of 2 filed