Substation Scout

Croydon substation interconnection queue

2 active projects totaling 11.5 MW in the PJM queue, plus 3 with terminal status (shown grayed).

5 PJM queue filings name Croydon as the point of interconnection, all in Bucks County, PA.

Target commercial operation dates as filed run from Dec 2002 to May 2010 (4 filings).

2active projects
11.5active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
G41 Croydon n/r 750 Gas Withdrawn n/r
T114 Croydon 230kV 230 32.5 Other Withdrawn May 2010
T115 Croydon 230kV 230 32.5 Other Withdrawn May 2010
E20 Croydon #11,12,21,22,31,32,41,42 230 6.5 Other In Service Dec 2002
U2-063 Croydon Generating Station 230 5 Gas In Service Jul 2008

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Bucks County, PA

All 19 PJM queue filings in Bucks County, PA.