Campbelltown-Millars Quarry substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
3 PJM queue filings name Campbelltown-Millars Quarry as the point of interconnection, all in Lebanon County, PA.
Target commercial operation date as filed: Jan 2027 (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF1-165 | East Ridge Solar | 69 | 9 | Solar | Withdrawn | Jan 2027 |
| AF1-211 | Palmyra Solar | 69 | 9 | Solar | Withdrawn | Jan 2027 |
| AF1-212 | Bellegrove Solar | 69 | 9 | Solar | Withdrawn | Jan 2027 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Lebanon County, PA
- South Lebanon: 1 active, 673 MW of 2 filed
- Ironwood: 2 active, 119.8 MW of 5 filed
- North Lebanon: 1 active, 3.2 MW of 3 filed
- N. Lebanon: 1 active, 1.2 MW of 2 filed
- Heidelberg: none active of 2 filed