Substation Scout

Moccasin Creek Solar

PJM queue ID AB2-059

Moccasin Creek Solar (AB2-059) is listed in the PJM interconnection queue as a 66 MW solar project in Edgecombe County, NC. The filing names Benson-Dunbar as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 15, 2020.

Queue IDAB2-059
Project nameMoccasin Creek Solar
Status (as published)In Service
SubstationBenson-Dunbar
Point of interconnectionBenson-Dunbar 115kV
CountyEdgecombe
StateNC
Voltage115 kV
Capacity66 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2020-06-15
Source datasetserial

Same substation and county

Benson-Dunbar substation: 2 requests in the PJM queue, 1 active totaling 66 MW.

Queue IDProjectMWResourceStatus
AI2-299Benson-Dunbar 115 kV30.8SolarWithdrawn

Edgecombe, NC: 23 requests in the PJM queue, 8 active totaling 341.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy100
MW capacity66
MFO100

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first