Olive Solar Facility
PJM queue ID Z2-114
Olive Solar Facility (Z2-114) is listed in the PJM interconnection queue as a 2.5 MW solar project in St. Joseph County, IN. The filing names Olive as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 15, 2016.
| Queue ID | Z2-114 |
|---|---|
| Project name | Olive Solar Facility |
| Status (as published) | In Service |
| Substation | Olive |
| Point of interconnection | Olive 12.47kV |
| County | St. Joseph |
| State | IN |
| Voltage | 12.5 kV |
| Capacity | 2.5 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2016-12-15 |
| Source dataset | serial |
Same substation and county
Olive substation: 2 requests in the PJM queue, 1 active totaling 2.5 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AH1-391 | Michiana Solar | 67 | Solar | Withdrawn |
St. Joseph, IN: 33 requests in the PJM queue, 11 active totaling 1,388.3 MW.
A substation with the same name is named in PJM transmission planning materials: Olive (AEP, 15 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 5 |
| MW capacity | 2.5 |
| MFO | 5 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.