Substation Scout

Kelford Solar Park

PJM queue ID Z2-043

Kelford Solar Park (Z2-043) is listed in the PJM interconnection queue as a 14 MW solar project in Bertie County, NC. The filing names Kelford as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2015.

Queue IDZ2-043
Project nameKelford Solar Park
Status (as published)In Service
SubstationKelford
Point of interconnectionKelford 34.5kV
CountyBertie
StateNC
Voltage34.5 kV
Capacity14 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2015-12-31
Source datasetserial

Same substation and county

Kelford substation: 4 requests in the PJM queue, 2 active totaling 16.1 MW.

Queue IDProjectMWResourceStatus
AA1-072Kelford Solar Park2.1SolarIn Service
R93Kelford 115kV12GasWithdrawn
W3-050Kelford 34.5kV7.6SolarWithdrawn

Bertie, NC: 30 requests in the PJM queue, 9 active totaling 591.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity14
MFO20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.