Kelford Solar Park
PJM queue ID AA1-072
Kelford Solar Park (AA1-072) is listed in the PJM interconnection queue as a 2.1 MW solar project in Bertie County, NC. The filing names Kelford as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2015.
| Queue ID | AA1-072 |
|---|---|
| Project name | Kelford Solar Park |
| Status (as published) | In Service |
| Substation | Kelford |
| Point of interconnection | Kelford 34.5kV |
| County | Bertie |
| State | NC |
| Voltage | 34.5 kV |
| Capacity | 2.1 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2015-12-31 |
| Source dataset | serial |
Same substation and county
Kelford substation: 4 requests in the PJM queue, 2 active totaling 16.1 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| Z2-043 | Kelford Solar Park | 14 | Solar | In Service |
| R93 | Kelford 115kV | 12 | Gas | Withdrawn |
| W3-050 | Kelford 34.5kV | 7.6 | Solar | Withdrawn |
Bertie, NC: 30 requests in the PJM queue, 9 active totaling 591.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 3.1 |
| MW capacity | 2.1 |
| MFO | 23.1 |