Substation Scout

Beaverbrook (Kinsley Solar)

PJM queue ID Y3-087

Queue IDY3-087
Project nameBeaverbrook (Kinsley Solar)
Status (as published)In Service
SubstationBeaverbrook
Point of interconnectionBeaverbrook 13kV
CountyGloucester
StateNJ
Voltage13 kV
Capacity1.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2015-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy3.8
Mw Capacity1.44
Mfo3.8

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.