Substation Scout

Tasley

PJM queue ID T66

Queue IDT66
Project nameTasley
Status (as published)In Service
SubstationTasley
Point of interconnectionTasley
CountyAccomack
StateVA
VoltageNot reported
Capacity6.7 MW
Resource (as published)Oil
Resource categoryOther (normalised for filtering)
Target commercial operation2009-03-26
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy6.7
Mw Capacity6.7
Mfo33

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.