Remington GT4
PJM queue ID S96
Remington GT4 (S96) is listed in the PJM interconnection queue as a 15 MW gas project in Fauquier County, VA. The filing names Remington as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2008.
| Queue ID | S96 |
|---|---|
| Project name | Remington GT4 |
| Status (as published) | In Service |
| Substation | Remington |
| Point of interconnection | Remington 230kV |
| County | Fauquier |
| State | VA |
| Voltage | 230 kV |
| Capacity | 15 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2008-06-01 |
| Source dataset | serial |
Same substation and county
Remington substation: 9 requests in the PJM queue, 6 active totaling 317.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-2173 | Remington 230 kV | 250 | Battery | Active |
| S93 | Remington GT1 | 15 | Gas | In Service |
| S94 | Remington GT2 | 15 | Gas | In Service |
| S95 | Remington GT3 | 15 | Gas | In Service |
| AB2-029 | Remington 34.5kV | 7.6 | Solar | In Service |
| AI2-001 | Remington 115 kV | 150 | Battery | Withdrawn |
| AG2-620 | Remington 230 kV | 100 | Battery | Withdrawn |
| AG2-178 | Remington 34.5 kV | 9.3 | Solar | Withdrawn |
Fauquier, VA: 52 requests in the PJM queue, 18 active totaling 2,367 MW.
A substation with the same name is named in PJM transmission planning materials: Remington (DOM, 6 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 15 |
| MW capacity | 15 |
| MFO | 190 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.