Substation Scout

Hay Road 1-3

PJM queue ID N05

Queue IDN05
Project nameHay Road 1-3
Status (as published)In Service
SubstationEdgemoor
Point of interconnectionEdgemoor 138kV
CountyNew Castle
StateDE
Voltage138 kV
Capacity9 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2004-08-09
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy9
Mw Capacity9
Mfo242

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.