Dubois 34.5 kV (C01-2127) is listed in the PJM interconnection queue as a 20 MW battery project in Clearfield County, PA. The filing names Dubois as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2028.

Queue IDC01-2127
Project nameDubois 34.5 kV
Status (as published)Active
SubstationDubois
Point of interconnectionDubois 34.5 kV
CountyClearfield
StatePA
Voltage34.5 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Same substation and county

Dubois substation: 2 requests in the PJM queue, 1 active totaling 20 MW.

Queue IDProjectMWResourceStatus
AH2-401Dubois 34.5 kV12SolarWithdrawn

Clearfield, PA: 53 requests in the PJM queue, 11 active totaling 840.5 MW.

A substation with the same name is named in PJM transmission planning materials: Dubois (PENELEC, 5 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperAM Energy Resources LLC
Transmission ownerPENELEC
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy20.0
MW capacity20.0
MFO20.0
Submitted date4/27/2026
Last updated6/3/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first