Substation Scout

Bremo 230 kV

PJM queue ID C01-2124

Queue IDC01-2124
Project nameBremo 230 kV
Status (as published)Active
SubstationBremo
Point of interconnectionBremo 230 kV
CountyFluvanna
StateVA
Voltage230 kV
Capacity780 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2033-03-31
Source datasetcycle

Additional filed fields

DeveloperTenaska Power Generation, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy800.0
Mw Capacity780.0
Mfo800.0
Submitted Date4/27/2026
Last Updated6/25/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.