Substation Scout

Wempletown 345 kV

PJM queue ID C01-2112

Queue IDC01-2112
Project nameWempletown 345 kV
Status (as published)Active
SubstationWempletown
Point of interconnectionWempletown 345 kV
CountyWinnebago
StateIL
Voltage345 kV
Capacity50 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-31
Source datasetcycle

Additional filed fields

DeveloperGemini Solar LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy250.0
Mw Capacity50.0
Mfo500.0
Submitted Date4/24/2026
Last Updated6/8/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.