Wempletown 345 kV

PJM queue ID C01-1796

Queue IDC01-1796
Project nameWempletown 345 kV
Status (as published)Active
SubstationWempletown
Point of interconnectionWempletown 345 kV
CountyWinnebago
StateIL
Voltage345 kV
Capacity50 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-31
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperGemini Solar LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy250.0
Mw Capacity50.0
Mfo250.0
Submitted Date4/24/2026
Last Updated9/30/2026