Maysville 25 kV (C01-1063) is listed in the PJM interconnection queue as a solar request filed at 0 MW (a net change or energy-only filing) in Mason County, KY. The filing names Maysville as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of August 31, 2027.
| Queue ID | C01-1063 |
|---|---|
| Project name | Maysville 25 kV |
| Status (as published) | Active |
| Substation | Maysville |
| Point of interconnection | Maysville 25 kV |
| County | Mason |
| State | KY |
| Voltage | 25 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-08-31 |
| Source dataset | cycle |
Same substation and county
Maysville substation: 3 requests in the PJM queue, 2 active totaling 30 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AE2-285 | MC Solar | 30 | Solar | Under Construction |
| AI2-467 | Maysville 138 kV | 5.8 | Solar | Withdrawn |
Mason, KY: 8 requests in the PJM queue, 3 active totaling 908 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | EDPR NA Distributed Generation LLC |
|---|---|
| Transmission owner | EKPC |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 8.65 |
| MW capacity | 0.0 |
| MFO | 8.65 |
| Submitted date | 4/17/2026 |
| Last updated | 10/2/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.