Substation Scout

Maysville 25 kV

PJM queue ID C01-1063

Queue IDC01-1063
Project nameMaysville 25 kV
Status (as published)Active
SubstationMaysville
Point of interconnectionMaysville 25 kV
CountyMason
StateKY
Voltage25 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-08-31
Source datasetcycle

Additional filed fields

DeveloperEDPR NA Distributed Generation LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy8.65
Mw Capacity0.0
Mfo8.65
Submitted Date4/17/2026
Last Updated6/29/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.