Mason, KY interconnection queue

3 active projects totalling 908 MW in the PJM queue, plus 5 with terminal status (shown greyed).

3active projects
908active MW
8total filed
Queue IDProjectkVMWResourceStatus
AB1-169 Mason Energy Center 345 1,100 Gas Withdrawn
C01-1227 Spurlock - Meldahl Dam 345 kV 345 758 Gas Active
AH1-756 Not reported n/r 250 Battery Withdrawn
AF2-111 Goldfinch Solar 345 150 Solar EP
Z2-061 Spurlock-Zimmer 345kV 345 88 Not reported Withdrawn
AF2-245 Spurlock-Flemingsburg 138 kV 138 79.2 Hybrid Withdrawn
AE2-235 Murphysville-Plumville 69 kV 69 41.9 Solar Withdrawn
C01-1063 Maysville 25 kV 25 0 Solar Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.