Substation Scout

Poseidon Storage

PJM queue ID AH1-249

Queue IDAH1-249
Project namePoseidon Storage
Status (as published)Active
SubstationLardin - Lake Lynn
Point of interconnectionLardin - Lake Lynn 138kV
CountyFayette
StatePA
Voltage138 kV
Capacity80 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperPoseidon Energy, LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StagePhase 3
Mw Energy80.0
Mw Capacity80.0
Mfo145.0
Submitted Date9/9/2021
Last Updated9/8/2026