Substation Scout

Poseidon Solar 2

PJM queue ID AH1-248

Poseidon Solar 2 (AH1-248) is listed in the PJM interconnection queue as a 15 MW solar project in Fayette County, PA. The filing names Lardin - Lake Lynn as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2028.

Queue IDAH1-248
Project namePoseidon Solar 2
Status (as published)Active
SubstationLardin - Lake Lynn
Point of interconnectionLardin - Lake Lynn 138kV
CountyFayette
StatePA
Voltage138 kV
Capacity15 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Same substation and county

Lardin - Lake Lynn substation: 3 requests in the PJM queue, 3 active totaling 119 MW.

Queue IDProjectMWResourceStatus
AH1-249Poseidon Storage80BatteryActive
AH1-247Poseidon Solar 124SolarActive

Fayette, PA: 56 requests in the PJM queue, 20 active totaling 6,162.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperPoseidon Energy, LLC
Transmission ownerAPS
Project typeGeneration Interconnection
CycleTC2
StagePhase 3
MW energy25.0
MW capacity15.0
MFO65.0
Submitted date9/9/2021
Last updated11/17/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first