Meadow Brook Storage
PJM queue ID AG2-300
Meadow Brook Storage (AG2-300) is listed in the PJM interconnection queue as a 70 MW battery project in Frederick County, VA. The filing names Meadow Brook as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2029.
| Queue ID | AG2-300 |
|---|---|
| Project name | Meadow Brook Storage |
| Status (as published) | Active |
| Substation | Meadow Brook |
| Point of interconnection | Meadow Brook 138 kV |
| County | Frederick |
| State | VA |
| Voltage | 138 kV |
| Capacity | 70 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-12-31 |
| Source dataset | cycle |
Same substation and county
Meadow Brook substation: 3 requests in the PJM queue, 1 active totaling 70 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| U2-088 | Meadow Brook 500kV | 0 | Not reported | Withdrawn |
| U3-005 | Meadow Brook | 0 | Not reported | Withdrawn |
Frederick, VA: 23 requests in the PJM queue, 11 active totaling 615.2 MW.
A substation with the same name is named in PJM transmission planning materials: Meadow Brook (APS, 8 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Meadow Brook Storage, LLC |
|---|---|
| Transmission owner | APS |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 100.0 |
| MW capacity | 70.0 |
| MFO | 100.0 |
| Submitted date | 3/23/2021 |
| Last updated | 11/5/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.