Substation Scout

Mayapple Solar

PJM queue ID AG1-349

Mayapple Solar (AG1-349) is listed in the PJM interconnection queue as a 156 MW solar project in Pulaski County, IN. The filing names Olive-Reynolds #2 as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of December 31, 2028.

Queue IDAG1-349
Project nameMayapple Solar
Status (as published)Engineering and Procurement
SubstationOlive-Reynolds #2
Point of interconnectionOlive-Reynolds #2 345 kV
CountyPulaski
StateIN
Voltage345 kV
Capacity156 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-12-31
Source datasetserial

Same substation and county

Olive-Reynolds #2 substation: 7 requests in the PJM queue, 3 active totaling 336 MW.

Queue IDProjectMWResourceStatus
AF2-205Moss Creek Solar120SolarEngineering and Procurement
AF2-134Mammoth North Solar Project60SolarIn Service
AF2-190Olive-Reynolds #2 345 kV156SolarWithdrawn
AH1-709Olive-Reynolds #2 345 kV80BatteryWithdrawn
AG2-117Olive-Reynolds #2 345 kV60HybridWithdrawn
AI2-357Olive-Reynolds #2 345 kV18.2SolarWithdrawn

Pulaski, IN: 21 requests in the PJM queue, 11 active totaling 1,270.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy260
MW capacity156
MFO260

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first