Red Maple Solar

PJM queue ID AG1-127

Queue IDAG1-127
Project nameRed Maple Solar
Status (as published)EP
SubstationCrego Rd
Point of interconnectionCrego Rd 138 kV
CountyDeKalb
StateIL
Voltage138 kV
Capacity57.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-05-31
Source datasetcycle

Additional filed fields

DeveloperRed Maple Solar, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy95.1
Mw Capacity57.1
Mfo190.0
Submitted Date8/31/2020
Last Updated4/13/2026