Red Maple Solar
PJM queue ID AF2-366
Red Maple Solar (AF2-366) is listed in the PJM interconnection queue as a 56.9 MW solar project in Adams County, IL. The filing names Crego Rd as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of February 7, 2028.
| Queue ID | AF2-366 |
|---|---|
| Project name | Red Maple Solar |
| Status (as published) | Engineering and Procurement |
| Substation | Crego Rd |
| Point of interconnection | Crego Rd 138 kV |
| County | Adams |
| State | IL |
| Voltage | 138 kV |
| Capacity | 56.9 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-02-07 |
| Source dataset | serial |
Same substation and county
Crego Rd substation: 2 requests in the PJM queue, 2 active totaling 114 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG1-127 | Red Maple Solar | 57.1 | Solar | EP |
Adams, IL: 8 requests in the PJM queue, 1 active totaling 56.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 94.9 |
| MW capacity | 56.94 |
| MFO | 94.9 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.