PJM queue ID AF1-215

Mammoth North Solar Project (AF1-215) is listed in the PJM interconnection queue as a 180 MW solar project in Starke County, IN. The filing names Olive-Reynolds as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of July 31, 2024.

Queue IDAF1-215
Project nameMammoth North Solar Project
Status (as published)In Service
SubstationOlive-Reynolds
Point of interconnectionOlive-Reynolds 345 kV
CountyStarke
StateIN
Voltage345 kV
Capacity180 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2024-07-31
Source datasetserial

Same substation and county

Olive-Reynolds substation: 6 requests in the PJM queue, 2 active totaling 264.3 MW.

Queue IDProjectMWResourceStatus
AE2-045Bottlebrush Solar84.3SolarUnder Construction
AI2-198Olive-Reynolds 345 kV108SolarWithdrawn
AI2-199Olive-Reynolds 345 kV108SolarWithdrawn
AD2-132Olive-Reynolds 345kV35.2WindWithdrawn
AC2-080Olive-Reynolds 345kV26WindWithdrawn

Starke, IN: 6 requests in the PJM queue, 3 active totaling 366 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy300
MW capacity180
MFO300

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first