Substation Scout

Clearview Solar I

PJM queue ID AF1-078

Clearview Solar I (AF1-078) is listed in the PJM interconnection queue as a 18.9 MW solar project in Champaign County, OH. The filing names East Sidney-Quincy as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 31, 2025.

Queue IDAF1-078
Project nameClearview Solar I
Status (as published)In Service
SubstationEast Sidney-Quincy
Point of interconnectionEast Sidney-Quincy 138 kV
CountyChampaign
StateOH
Voltage138 kV
Capacity18.9 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2025-01-31
Source datasetserial

Same substation and county

East Sidney-Quincy substation: 5 requests in the PJM queue, 3 active totaling 86.4 MW.

Queue IDProjectMWResourceStatus
AE2-206Clearview Solar I41.6SolarIn Service
AG2-216East Sidney-Quincy 138 kV25.9SolarActive
AI2-242East Sidney-Quincy 138 kV63SolarWithdrawn
AG2-004East Sidney-Quincy 138 kV8.4SolarWithdrawn

Champaign, OH: 32 requests in the PJM queue, 5 active totaling 316.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy45
MW capacity18.9
MFO144

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first