Substation Scout

Clearview Solar I

PJM queue ID AE2-206

Queue IDAE2-206
Project nameClearview Solar I
Status (as published)In Service
SubstationEast Sidney-Quincy
Point of interconnectionEast Sidney-Quincy 138 kV
CountyChampaign
StateOH
Voltage138 kV
Capacity41.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-01-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy99
Mw Capacity41.58
Mfo99

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.