Sandy Ridge (AD2-133) is listed in the PJM interconnection queue as a 15.3 MW wind project in Centre County, PA. The filing names Eagle Valley as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of July 31, 2023.
| Queue ID | AD2-133 |
|---|---|
| Project name | Sandy Ridge |
| Status (as published) | In Service |
| Substation | Eagle Valley |
| Point of interconnection | Eagle Valley 115kV |
| County | Centre |
| State | PA |
| Voltage | 115 kV |
| Capacity | 15.3 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2023-07-31 |
| Source dataset | serial |
Same substation and county
Eagle Valley substation: 2 requests in the PJM queue, 2 active totaling 63.9 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-1275 | Eagle Valley 115 kV | 48.6 | Wind | Active |
Centre, PA: 53 requests in the PJM queue, 9 active totaling 212.9 MW.
A substation with the same name is named in PJM transmission planning materials: Eagle Valley (PENELEC, 2 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 85.4 |
| MW capacity | 15.3 |
| MFO | 135.4 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.