Raceway Solar (AC2-186) is listed in the PJM interconnection queue as a 3.8 MW solar project in Kent County, DE. The filing names Harrington as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of August 1, 2027.
| Queue ID | AC2-186 |
|---|---|
| Project name | Raceway Solar |
| Status (as published) | Under Construction |
| Substation | Harrington |
| Point of interconnection | Harrington 25kV |
| County | Kent |
| State | DE |
| Voltage | 25 kV |
| Capacity | 3.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-08-01 |
| Source dataset | serial |
Same substation and county
Harrington substation: 8 requests in the PJM queue, 4 active totaling 39 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| C01-1949 | Harrington 69 kV | 20 | Solar | Active |
| AC2-187 | Raceway Solar | 7.6 | Solar | Under Construction |
| AC2-188 | Raceway Solar | 7.6 | Solar | Under Construction |
| AI2-090 | Harrington 69 kV | 31 | Solar | Withdrawn |
| AG1-464 | Harrington 69 kV | 20 | Battery | Withdrawn |
| AH1-574 | Harrington 69kV | 12 | Solar | Withdrawn |
| AH1-575 | Harrington 69kV | 6 | Solar | Withdrawn |
Kent, DE: 34 requests in the PJM queue, 13 active totaling 320.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 10 |
| MW capacity | 3.8 |
| MFO | 10 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.