Substation Scout

Aurora Generation

PJM queue ID AC1-111

Aurora Generation (AC1-111) is listed in the PJM interconnection queue as a 36 MW gas project in Du Page County, IL. The filing names Aurora as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2020.

Queue IDAC1-111
Project nameAurora Generation
Status (as published)In Service
SubstationAurora
Point of interconnectionAurora 138kV
CountyDu Page
StateIL
Voltage138 kV
Capacity36 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2020-12-31
Source datasetserial

Same substation and county

Aurora substation: 4 requests in the PJM queue, 4 active totaling 100 MW.

Queue IDProjectMWResourceStatus
AC1-109Aurora Generation30GasIn Service
AC1-110Aurora Generation30GasIn Service
AG1-513Aurora Battery Storage4BatterySuspended

Du Page, IL: 6 requests in the PJM queue, 3 active totaling 96 MW.

A substation with the same name is named in PJM transmission planning materials: Aurora (COMED, 2 mentions).

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy36
MW capacity36
MFO1016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first