PJM queue ID AC1-086

Cherry Solar (AC1-086) is listed in the PJM interconnection queue as a 123.7 MW solar project in Northhampton County, NC. The filing names Thelma as its point of interconnection. PJM lists its status as “Partially in Service - Under Construction”, with a target commercial operation date of March 23, 2027.

Queue IDAC1-086
Project nameCherry Solar
Status (as published)Partially in Service - Under Construction
SubstationThelma
Point of interconnectionThelma 230kV
CountyNorthhampton
StateNC
Voltage230 kV
Capacity123.7 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-03-23
Source datasetserial

Same substation and county

Thelma substation: 4 requests in the PJM queue, 2 active totaling 207.7 MW.

Queue IDProjectMWResourceStatus
AB1-132Oak Solar84SolarIn Service
AG1-106Oak Solar16SolarWithdrawn
AG2-237Thelma 230kV0BatteryWithdrawn

Northhampton, NC: 18 requests in the PJM queue, 5 active totaling 313.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy180
MW capacity123.7
MFO180

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first