Oak Solar

PJM queue ID AB1-132

Queue IDAB1-132
Project nameOak Solar
Status (as published)In Service
SubstationThelma
Point of interconnectionThelma 230kV
CountyNorthhampton
StateNC
Voltage230 kV
Capacity84 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-25
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy120
Mw Capacity84
Mfo120

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.